Demo environment — data may be reset without notice. Not for production use.
VanillaPM
Sign in Get started free
Pr8 Process · 41%

Plan and manage schedule

In the app: Project → Gantt (Timeline · List · Variance)

PMP ECO · Process (41%) · Task Pr8. Turn the scope into a sequenced, estimated, baselined timeline — find the critical path, protect it, and control against the baseline as reality lands.

What it is

Schedule development runs: define activities → sequence them (dependencies, leads/lags) → estimate durationsdevelop the schedulecontrol it. The Critical Path Method (CPM) finds the longest path of dependent activities — the critical path — and each activity's float/slack (how much it can slip before it delays the project). To compress a schedule you can crash (add resources — costs money) or fast-track (run activities in parallel — adds risk). Uncertain durations can be estimated with PERT (three-point: (O + 4M + P) / 6).

Why it matters

  • The critical path is where schedule risk lives — a day lost on it is a day lost on the project; a day lost off it may cost nothing.
  • A baseline is what makes "are we behind?" a measurable question instead of a feeling.

Where you do it in VanillaPM

The Gantt workspace (Timeline · List · Variance) gives CPM/float, a baseline to freeze the plan, PERT three-point estimation, and variance (baseline vs actual). The schedule sequences the WBS work packages and drives the Earned-Value schedule indices.

Walked example — Coral Ridge Resort

Coral Ridge's critical path runs design → coastal/ECA clearance → piling (−22 m) → raft & basement → RCC frame 1–5 → frame 6–10 → sea-facing curtain wall → MEP → fit-out → commissioning — each step gates the next, so the clearance and the frame cycles carry no slack. Because piling on unknown coastal strata is uncertain, its duration is PERT-estimated. To chase the peak-season open, the team fast-tracks the sea-view fit-out stack (starting fit-out on lower floors while upper floors are still framing) — buying schedule at the cost of added coordination risk. The baseline vs actual view shows where the monsoon pushed the frame and how the recovery is tracking.

The Gantt with the critical path

Baseline vs actual variance

The artefact

  • Schedule baseline + Gantt (critical path, float), with PERT estimates and variance tracking.

Best practices & pitfalls

  • Do know your critical path and guard it — that's where to focus attention and reserve.
  • Do choose compression with eyes open: crashing costs money, fast-tracking adds risk; neither is free.
  • Pitfall: managing to the baseline dates while ignoring the critical path — a slip off the path may not matter; a slip on it always does.

On the PMP exam

Schedule is technique-heavy: critical path, total vs free float, forward/backward pass, crashing vs fast-tracking, leads and lags, and PERT three-point estimating. Expect to identify the critical path from a network diagram and to pick the right compression method for a given constraint (cost-sensitive → fast-track; risk-sensitive → crash).