Demo environment — data may be reset without notice. Not for production use.
VanillaPM
Sign in Get started free Dashboard
★ Reference Reference

ITTO cheat sheet — the PMBOK 8e processes, done in VanillaPM

In the app: The whole project workspace — each process maps to a tab below

ITTO = Inputs · Tools & Techniques · Outputs. It's the skeleton of the PMBOK® Guide: every process turns some inputs into outputs using a set of tools & techniques. This one page is the whole 8th edition — 40 processes across 7 performance domains — condensed to the essentials, with a column showing where you actually do each one in VanillaPM and a link to the walked tutorial task.

New to ITTO? Read ITTO explained first — the same idea walked through one Coral Ridge thread, which makes this grid readable instead of a wall. This page is the lookup; that one is the why.

Read it top-to-bottom once for the shape of the discipline; then keep it open as a map while you work through the tasks. The lists are illustrative, not exhaustive (the 8th edition marks them so) — the "key" items are the ones you'll reach for most.

▶ Play PMP Reps — once you've read this, drill it into memory with spaced-repetition flashcards: a coach, a glossary, streaks and levels (no login).

Everything below is demonstrated on the same running example — the Coral Ridge Resort build (python manage.py seed_tutorial). Start the walk at P1 · Develop a common vision.

The map — 7 performance domains × 5 focus areas

Domain Initiating Planning Executing Monitoring & Controlling Closing
Governance Initiate Project Integrate Plans · Plan Sourcing Manage Execution · Manage QA · Manage Knowledge Monitor Performance · Assess Changes Close Project
Scope — Plan Scope · Requirements · Define Scope · Scope Structure — Monitor Scope · Validate Scope —
Schedule — Plan Schedule · Develop Schedule — Monitor Schedule —
Finance — Plan Finance · Estimate Costs · Develop Budget — Monitor Finances —
Stakeholders Identify Stakeholders Plan Engagement · Plan Communications Manage Engagement · Manage Communications Monitor Engagement · Monitor Communications —
Resources — Plan Resources · Estimate Resources Acquire Resources · Lead the Team Monitor Resourcing —
Risk — Plan Risk · Identify · Analyse · Plan Responses Implement Responses Monitor Risks —

1 · Governance

Process Group Inputs (I) Tools and Techniques (TT) Outputs (O) In VanillaPM
Initiate Project or Phase Init. Business case, benefits plan, agreements Expert judgment, brainstorming, project canvas Project charter, assumption log Project → Charter · B1
Integrate & Align Plans Plan Charter, outputs of other processes Expert judgment, meetings, project canvas Project management plan Planning → Integrated Plan · Pr1
Plan Sourcing Strategy Plan Charter, plan, requirements, risk register Make-or-buy, source-selection analysis, market research Sourcing strategy plan Planning → Procurement · Pr5
Manage Project Execution Exec. Plan, approved changes, project docs PMIS, daily coordination meetings Deliverables, work performance data, issues Project → Tasks / Kanban · Pr3
Manage Quality Assurance Exec. Plan, project docs, policies Audits, checklists, process improvement Quality reports, change requests Planning → Quality Plan · Control → Quality control · Pr7
Manage Project Knowledge Exec. Plan, lessons register, deliverables Knowledge management, retrospectives, storytelling Lessons learned register Project → Knowledge / Knowledge Base · P7
Monitor & Control Performance M&C Plan, work performance info, forecasts Earned value analysis, trend/variance analysis, dashboards Work performance reports, change requests Project → Control → Overview · Pr9
Assess & Implement Changes M&C Baselines, change requests, change log Integrated change control, CCB decision-making Approved change requests, updated baselines Project → Control → Change requests · B3
Close Project or Phase Close Plan, accepted deliverables, agreements Document analysis, variance/trend analysis, meetings Final report, transition, archive Project → Closeout · Pr10

2 · Scope

Process Group Inputs (I) Tools and Techniques (TT) Outputs (O) In VanillaPM
Plan Scope Management Plan Charter, plan Expert judgment, data gathering Scope & requirements mgmt plans Planning → Scope (Management Plan) · Pr2
Elicit & Analyze Requirements Plan Charter, business case, stakeholder register Interviews, workshops, prioritisation, design thinking Requirements documentation Planning → Requirements · Pr2
Define Scope Plan Charter, requirements Expert judgment, product analysis, decomposition Project scope statement Planning → Scope → Statement · Pr2
Develop Scope Structure Plan Scope statement, requirements Decomposition, brainstorming Scope baseline, WBS, WBS dictionary Project → WBS · Pr2
Monitor & Control Scope M&C Plan, requirements, deliverables Variance/trend analysis, inspections Verified deliverables, change requests Project → WBS (scope validation) · Pr9
Validate Scope M&C Requirements, verified deliverables Inspection, review meetings, customer tests Accepted deliverables Project → WBS (deliverable acceptance) · Pr2

3 · Schedule

Process Group Inputs (I) Tools and Techniques (TT) Outputs (O) In VanillaPM
Plan Schedule Management Plan Charter, plan, development approach Expert judgment, alternatives analysis Schedule management plan Planning → Schedule Mgmt Plan · Pr8
Develop Schedule Plan Activity list, durations, dependencies, resources Critical path method, estimation, compression, leveling Schedule baseline, project schedule Project → Gantt · Schedule Baseline · Pr8
Monitor & Control Schedule M&C Plan, schedule, work performance data Earned value / earned schedule, burndown, what-if Schedule forecasts, change requests Project → Gantt → Variance · Control → Overview · Pr8

4 · Finance

Process Group Inputs (I) Tools and Techniques (TT) Outputs (O) In VanillaPM
Plan Financial Management Plan Charter, schedule & risk plans Expert judgment, alternatives analysis Financial management plan, funding strategy Planning → Financial Mgmt Plan · Pr6
Estimate Costs Plan Scope baseline, schedule, resources Analogous/parametric/bottom-up, three-point, cost of quality Cost estimates, basis of estimates Planning → Estimate · Pr6
Develop Budget Plan Cost estimates, scope baseline Cost aggregation, reserve analysis Cost baseline, funding requirements Project → Budget · Budget Reserves · Pr6
Monitor & Control Finances M&C Cost baseline, work performance data Earned value, TCPI, reserve analysis Cost forecasts, change requests Project → Control → Overview (EVM) · Pr6

5 · Stakeholders

Process Group Inputs (I) Tools and Techniques (TT) Outputs (O) In VanillaPM
Identify Stakeholders Init. Charter, business docs Stakeholder analysis, stakeholder mapping Stakeholder register Project → Stakeholders → Register · P4
Plan Stakeholder Engagement Plan Charter, stakeholder register Engagement assessment matrix, prioritisation Stakeholder engagement plan Project → Stakeholders (engagement) · P5
Plan Communications Management Plan Stakeholder register, engagement plan Communication requirements analysis, methods/models Communications management plan Planning → Comms Plan · P8
Manage Stakeholder Engagement Exec. Comms & engagement plans, issue log Feedback, negotiation, conflict management Change requests, updated logs Stakeholders → Register → Interaction Log · P6
Manage Communications Exec. Comms plan, work performance reports Communication methods/tech, project reporting Project communications Planning → Comms Plan → Schedule · P8
Monitor Stakeholder Engagement M&C Engagement plan, project communications Stakeholder analysis, engagement assessment matrix Change requests, updated register Stakeholders (current→target engagement) · P6
Monitor Communications M&C Comms plan, work performance data PMIS, engagement assessment matrix Work performance info Planning → Comms Plan · P8

6 · Resources

Process Group Inputs (I) Tools and Techniques (TT) Outputs (O) In VanillaPM
Plan Resource Management Plan Charter, scope baseline RACI / responsibility matrix, org theory Resource plan, team charter Planning → Resources · Team → Charter · Pr4
Estimate Resources Plan Activity list, resource plan Bottom-up/analogous/parametric estimating Resource requirements, RBS Planning → Resources · Pr4
Acquire Resources Exec. Resource plan, cost baseline Negotiation, pre-assignment, virtual teams Team & resource assignments Team · Org → Staff allocation · Pr4
Lead the Team Exec. Resource plan, team charter, assessments Team building, recognition, coaching, servant leadership, Tuckman Team performance assessments Project → Team (charter · health · recognition · conflicts) · P3
Monitor & Control Resourcing M&C Resource plan, work performance data Performance reviews, negotiation, control charts Change requests, updated plan Project → Team → Workload · Resources · Pr4

7 · Risk

Process Group Inputs (I) Tools and Techniques (TT) Outputs (O) In VanillaPM
Plan Risk Management Plan Charter, plan, stakeholder register Expert judgment, meetings Risk management plan Planning → Risk Mgmt Plan · B5
Identify Risks Plan Plans, baselines, project docs Brainstorming, checklists, SWOT, prompt lists Risk register, risk report Project → Risks (Register) · B5
Perform Risk Analysis Plan Risk register, baselines Probability & impact matrix, simulation, decision trees, sensitivity Prioritised risks (register update) Project → Risks (EMV · heat-map) · B5
Plan Risk Responses Plan Risk register, risk report Threat/opportunity strategies, contingent responses Change requests, updated register Project → Risks (responses) · B5
Implement Risk Responses Exec. Risk mgmt plan, risk register Influencing, PMIS Change requests, updated register Project → Risks · B5
Monitor Risks M&C Risk register, work performance data Reserve analysis, technical performance analysis, audits Work performance info, change requests Project → Control → Overview (risk status) · Risks · B5

Condensed from the PMBOK® Guide 8th Edition (PMI, Nov 2025), Section 2. Lists are illustrative, not exhaustive. Quality, Communications and Procurement are folded into their owning domains (Governance, Stakeholders, Resources). PMBOK and PMP are registered marks of the Project Management Institute, Inc.