Demo environment — data may be reset without notice. Not for production use.
VanillaPM
Sign in Get started free Dashboard
Pr5 Process · 41%

Plan and manage procurement

In the app: Planning → Procurement (Overview · Plan · Items) · Planning → Vendors

PMP ECO · Process (41%) · Task Pr5. Decide what to buy, choose the contract that puts each risk where it belongs, order in time for the work, and manage each contract to its close.

Who carries the risk, and when to order — the short version

What it is

Procurement runs in three parts:

  1. Plan. For each part of the work, decide make or buy. For what you buy, choose a contract type, write the statement of work, and set the source selection criteria you'll judge bids by.
  2. Conduct. Invite bids, evaluate them against the criteria, select a seller, sign.
  3. Control. Manage the contract, its changes and claims, and close it: deliverables accepted, final account agreed, supplier performance recorded.

The contract type decides who carries the cost risk:

Type Use it when Cost risk sits with
Fixed price (lump sum) The work is predictable and the requirements are well defined The seller
Cost plus (cost-reimbursable) The work is evolving, likely to change or not well defined The buyer
Time & material The scope is still being worked out; rates are agreed, quantity isn't Shared

Then there's time. Every package has a lead time (from order to delivery on site), and lead time counts backwards from the date the work needs it:

Order by = needed on site − lead time.

Miss the order-by date and the package arrives late, however good the contract.

Why it matters

  • Most of the budget is bought, not built in-house. On a construction project, procurement is the biggest lever on cost and risk.
  • The wrong contract type puts risk on the party least able to control it. Fixed price on unknown ground invites claims; cost plus on a fully specified product gives away cost control.
  • Long-lead items drive the schedule. Imported equipment with a 40-week lead time is on the critical path long before anyone installs it.
  • The lowest price is not the best bid. Source selection weighs capability, delivery and life-cycle cost alongside price.

Where you do it in VanillaPM

  • Planning → Procurement → Overview shows the packages and their value, who carries the cost risk by contract type, an order timeline (needed on site, order by, timing) and the open source selections with each bid.
  • Items is the procurement register: each package with its WBS work, supplier, contract type and its cost risk, value, order-by date with a timing badge (Ordered, On track, Order soon, Order late) and status. Close records the closure notes and a supplier rating.
  • Plan is the governed procurement management plan: make-or-buy approach, contract types, source selection criteria and closure.
  • Vendors links suppliers from the organisation's directory to this project's packages, with each one's RFP status and quote.
  • The integrated plan (Pr1) checks Procurement is ahead of the work, and fails while any package is late.

Free tools: Procurement management plan template (Word, Markdown) · Order-by date calculator.

Walked example — Coral Ridge Resort

Coral Ridge buys six packages worth USD 16.9M, and each contract type was chosen for how certain the scope was. The piling went cost plus: nobody knew the ground below 15 metres, so the owner carried that risk, and it materialised: the ground was softer than the survey showed, and the package closed USD 0.2M over, rated 3/5, with the lesson to drill more boreholes before tendering. Early enabling works went time & material while the site survey was still moving. The facade, lifts, HVAC and FF&E are fixed price because their specifications are complete.

The finding is timing. The HVAC chillers are needed on site on 2 September 2027 for the MEP first fix. They're imported, with a 42-week lead time, so they had to be ordered by 12 November 2026. They're still being sourced. Three bids are in: the cheapest is slowest and has no coastal-corrosion warranty; the best technical bid can deliver six weeks sooner from stock. Picking it closes part of the gap.

The workspace — the theory behind each screen

Every screenshot is the actual sample project, not a mock-up.


1 · Contract types and order dates

The theory: procurement strategy and lead time. Choose the contract type by scope certainty, and work out each package's order-by date from when the work needs it, less its lead time.

Coral Ridge — procurement overview and order timeline
Coral Ridge — procurement overview and order timeline

Reading the screenshot: 6 packages · USD 16.9M, 2 not yet contracted. Orders: 1 late. Who carries the cost risk: USD 15.3M with the sellers (fixed price), USD 400,000 shared (time & material), USD 1.2M with the buyer (cost plus). The order timeline sorts the packages by order-by date. HVAC & chillers: needed on site 2 Sep 2027, 294-day lead time, order by 12 Nov 2026, Order late. Everything else is ordered or on track.

✅ Do work out the order-by date for every long-lead package as soon as the schedule is set.
❌ Avoid treating procurement as something that starts when the work does. By then it's late.


2 · Source selection: the best bid, not the cheapest

The theory: source selection criteria. Agree before the bids arrive how they'll be judged: capability, technical approach, delivery, life-cycle cost and price. Then apply it. A non-compliant bid is rejected, however cheap.

Coral Ridge — source selection for the HVAC package
Coral Ridge — source selection for the HVAC package

Reading the screenshot: weighted per the procurement plan: technical 50%, price 35%, delivery 15%. Gulf Chiller Co. is Rejected: its chillers miss the specified efficiency. Bengal Climate Engineering is cheapest at USD 2.9M, but 46-week delivery makes the lateness worse, and there's no corrosion warranty on a coastal site. Polar Air Systems, USD 3.0M, has the best technical score and can deliver six weeks sooner from stock. On these criteria it's the better bid, and the faster one.

✅ Do set the evaluation weights in the plan, before any bid is opened.
❌ Avoid choosing on price alone, especially for equipment that has to survive salt air.


3 · The register: risk, timing and closure in one view

The theory: control and close procurements. Track each contract to its close: its status, its order date, and at the end a closure record with the supplier's performance and lessons.

Coral Ridge — the procurement register
Coral Ridge — the procurement register

Reading the screenshot: each package shows its WBS work, contract type and who carries the cost risk, value, order-by date with its timing, and status. Two are Closed with ratings: early enabling works 4/5 (time & material, on time, rates held) and piling 3/5 (cost plus, over because the ground was worse than surveyed). HVAC shows Bids in and Order late.

✅ Do close every contract formally, with a rating and the lesson learned.
❌ Avoid leaving finished contracts open. Unclosed contracts carry claims and retentions nobody is watching.

Best practices & pitfalls

  • Do match contract type to scope certainty: well defined → fixed price; uncertain → cost plus or time & material.
  • Do write a clear statement of work. Ambiguity there becomes a change order later.
  • Do count lead time back from the date the work needs the item.
  • Pitfall: the lowest bid on price alone. Weight capability, delivery and risk too.
  • Pitfall: fixed price on work nobody can define yet. The seller prices in the risk, or claims it later.

On the PMP exam

Know the contract families and who carries the risk: fixed price → seller, cost-reimbursable → buyer, time & material → in between and suited to undefined scope. Know the make-or-buy decision, the procurement statement of work, source selection criteria and that contract closure includes accepting deliverables, settling claims and recording supplier performance. In scenarios, the PM works through the contract and the procurement process: changes go through the contract's change procedure, and the buyer doesn't instruct the seller's staff directly.

Check your understanding a short quiz — pass to mark the task complete