Free calculator

Communication channels calculator

A free communication channels calculator — enter the number of people to get the number of communication channels, n(n − 1) / 2, and see how many are added when people join.

Channels nown(n − 1) ÷ 2
After they join(n + k)(n + k − 1) ÷ 2
Added
Channels = n(n − 1) ÷ 2
After = (n + k)(n + k − 1) ÷ 2
Download as Excel (.xlsx) The spreadsheet has live formulas: change the yellow cells and it recalculates.

The formula

Every pair of people who might talk to each other is one channel. With n people there are n(n − 1) ÷ 2 channels: 5 people have 10, 10 have 45, 20 have 190.

Why it matters

Communication effort grows far faster than the head count. Adding two people to a team of eight adds 17 channels, not two. That's why larger projects need a planned structure (a communications plan) rather than everyone talking to everyone, and why a late addition to the team can slow things down before it speeds them up.

On the PMP exam

Questions often give a team size, add a few people, and ask how many channels were added. Work out both totals and subtract; the calculator shows each step.

See it used on a real project: P8 · Plan and manage communication