Decision tree and EMV calculator

A free decision tree and expected monetary value (EMV) calculator. Enter each option's up-front cost and its possible outcomes with their chances, and see the expected cost or value of every option, worked through.

Download as Excel (.xlsx) The spreadsheet has live formulas: change the yellow cells and it recalculates.

What EMV is

Expected monetary value puts a number on an uncertain outcome: multiply what each outcome would cost (or earn) by its chance of happening, and add them up. A 30% chance of a 50,000 overrun has an EMV of 15,000. It isn't what will happen (that's either 0 or 50,000); it's what the risk is worth on average, which is what you need to compare options fairly.

How a decision tree uses it

A decision tree lays out the choices you can make and, after each one, the things that might happen. For each option:

  1. Work out the EMV of its outcomes.
  2. Add the option's up-front cost (if the values are costs), or subtract it (if they're gains).
  3. Pick the option with the lowest expected cost, or the highest expected value.

The example is from the Coral Ridge Resort sample: test the piles before the raft foundation for 40,000, or skip the test and risk a 300,000 redesign if a soft layer turns up. Testing costs money every time, but its expected cost (55,000) is far below skipping it (90,000).

Things to watch

  • Each option's chances must add up to 100%. The calculator warns you when they don't.
  • Use the same sign throughout: all costs, or all gains. Mixing them gives nonsense.
  • EMV suits decisions you make many times, or that are small relative to the budget. For one large, rare loss, the organisation's appetite for risk matters as much as the average.

On the PMP exam

Expect a small tree with two options and two or three branches each. Calculate each branch, add the option's cost, and compare. Read carefully whether the numbers are costs or gains.

See it used on a real project: B5 · Plan and manage risk