Measure performance with Earned Value
Learn Finance · Project & Cost Finance · Task A4. Turn "are we on track?" into four numbers you can act on — cost and schedule, from one method.
Drill every EVM formula as flashcards in PMP Reps → Finance · Cost & EVM.
What it is
Earned Value Management (EVM) combines scope, schedule, and cost into one set of numbers. It rests on three values at a point in time (the data date):
- PV — Planned Value: the budgeted cost of the work that should be done by now (the baseline's S-curve).
- EV — Earned Value: the budgeted cost of the work actually completed ("how much value have we earned?").
- AC — Actual Cost: what you've actually spent on that work.
From those three come the four indices:
| Metric | Formula | Reads |
|---|---|---|
| CV — cost variance | EV − AC | +under budget / −over |
| SV — schedule variance | EV − PV | +ahead / −behind (in money) |
| CPI — cost performance index | EV ÷ AC | >1 under budget |
| SPI — schedule performance index | EV ÷ PV | >1 ahead of schedule |
Why it matters
- "80% done" is a feeling; CPI is a fact. EVM replaces optimistic status with a measured rate of cost and schedule efficiency.
- It catches trouble early. A CPI of 0.85 at the halfway point is a number you can escalate now, not a surprise at the end.
- It's the input to forecasting (A5) — EAC and TCPI are built on CPI/SPI.
Where you do it in VanillaPM
Everything below is in Project → Control → Overview (apps/budget/evm.py). A step-by-step:
-
Set the data date. Pick the as-of date you're measuring at — every figure below is "as of" that point.
-
Three inputs line up automatically. PV (planned value) comes from the time-phased cost baseline (A2); EV (earned value) from WBS/task completion against that baseline; AC (actual cost) from the actuals (A3). You don't type these — they're read from the project.
-
Read the indices.
derive_indices(pv, ev, ac, bac)computes CV = EV − AC, SV = EV − PV, CPI = EV ÷ AC, SPI = EV ÷ PV, each with a health flag (an index below 1.0 is over cost / behind schedule).
Step 3 — the indices at the data date: PV $994k · EV $850k · AC $1.0M → SPI 0.85 and CPI 0.85, both at risk -
Read the three-curve chart. The dashboard plots PV, EV and AC over time — the gap between EV and AC is your cost variance; between EV and PV, your schedule variance. One glance tells you where the project stands.

Step 4 — the PV / EV / AC three-curve chart: EV trails PV (behind) and AC runs above EV (over budget)
Walked example — Meridian
At month 9 of the 18-month, $2M build:
| Value | |
|---|---|
| PV (planned by now) | 1,000,000 |
| EV (work actually done, at budget) | 850,000 |
| AC (actually spent) | 1,000,000 |
- CV = EV − AC = 850 − 1000 = −$150,000 (over budget)
- SV = EV − PV = 850 − 1000 = −$150,000 (behind schedule)
- CPI = EV ÷ AC = 850 ÷ 1000 = 0.85 (85 cents of value per dollar spent)
- SPI = EV ÷ PV = 850 ÷ 1000 = 0.85 (85% of planned work done)
Meridian is over budget and behind — and you know it at the halfway mark, with numbers to take to the sponsor.
The numbers
The intuition in one line: EV is the hinge. Compare EV to AC → cost; compare EV to PV → schedule. A variance is a dollar (EV−AC); an index is a ratio (EV÷AC). At CPI 0.85, every planned dollar is buying 85 cents of work — which is exactly why the forecast (A5) lands above BAC.
Controls & assurance
- EV measured against the baseline (A2) — not against a moving target.
- An honest EV rule (% complete, milestones) applied consistently — gaming EV breaks everything downstream.
- AC that ties to the actuals ledger, at the same data date as EV.
- Indices reported with the three-curve chart, so the trend (not just today's point) is visible.
Best practices & pitfalls
- Do read cost and schedule separately — a project can be on budget but late (CPI 1.0, SPI 0.8) or vice versa.
- Do watch the trend in CPI, not one reading.
- Pitfall: confusing SV (money) with calendar time. SV is in dollars; for time, use earned schedule.
- Pitfall: inflating EV to look healthy. EV is budgeted cost of completed work — claiming work that isn't done just hides the problem until the finish.
Practise question
Q1. PV = $600k, EV = $540k, AC = $450k. Compute CV, SV, CPI, SPI — and say in one sentence what's happening.
Answer: CV = 540 − 450 = +$90k; SV = 540 − 600 = −$60k; CPI = 540/450 = 1.2; SPI = 540/600 = 0.9. The project is under budget but behind schedule — efficient with money, slower than planned.
Your hands-on assignment
Reading about EV is one thing — go produce it. In a demo project that has a cost baseline (your figures will differ from Meridian's, and that's fine):
- Open Budget → Earned Value on a project with an approved baseline.
- Read the CPI and SPI the app computes at the current data date.
- Say out loud whether the project is over or under budget (CPI) and ahead of or behind schedule (SPI).
- Find the EAC forecast and note what it implies for the final cost.
- Change one actual cost and watch CPI and the variance move — then put it back.
When you've done it, test yourself with the knowledge check below — a short quiz drawn from this lesson. Score 80% or more and the lesson is marked complete.
Terms used here
- PV / EV / AC — planned value, earned value, actual cost at the data date.
- CV / SV — cost / schedule variance (dollars).
- CPI / SPI — cost / schedule performance index (ratios).
- Data date — the "as of" point the measurement is taken.
- Related: Forecast to completion — turning today's CPI/SPI into the projected finish.
What the sponsor / PMO expects
CPI and SPI reported each period against a stable baseline, with an honest EV rule. Those two ratios are the universal language of project status — a sponsor reads 0.85/0.85 and knows exactly where Meridian stands without a single adjective.
Sign in to track your progress and earn your track completion.
🎉 You finished the track — view your completion →